Answer:
Where there is a negative schedule variance (SV), the project is said to be behind schedule
Where there is a negative cost variance (CV) the project is said to be over budget
Step-by-step explanation:
Schedule variance is found by subtracting the cost of work scheduled from the cost of performed work
It is given by;
Schedule variance (SV) = Cost of performed work - Cost of work scheduled
or
Schedule variance (SV) = BCWP - BCWS
Where
BCWP = Budgeted Cost of Work Performed
BCWS = Budgeted Cost of Work Scheduled
Schedule variance (SV) = Earned Value (EV) - Planned Value (PV)
Where there is a negative schedule variance, the project is said to be behind schedule.
Cost variance (CV) is given by;
Cost variance is found by subtracting the actual cost (AC) of a project from the expected cost (EC) of the project.
CV = EV - AC = EC - AC
Where there is a negative cost variance the project is said to be over budget.