I would love to answer but unfortunately there is no picture.
The project is going to scope if the situation happens. Option A is correct.
<h3 /><h3>What is the function of a project manager?</h3>
Project managers are in charge of organizing, planning, and guiding the execution of certain projects for an organization .
As the project manager, you grant a team member's request to rearrange their work in a way they believe will increase productivity.
However, this modification interferes with another team member's workflow since they now have to complete two more activities that are unrelated to the project's objective. The project will be within its scope.
Hence option A is correct.
To learn more about the project manager refer;
brainly.com/question/15404120
#SPJ1
Answer:
Ethics
Explanation:
To do the right thing or to have moral principles is called ethics. Ethics affect how people make decisions and lead their lives. Some words people associate with ethics includes:
- Honesty
- Integrity
- Promise keeping and Trustworthiness
- Loyalty
- Fairness
- Concern for others
- Respect for others
- Law abiding
etc.
Answer:
2.0%
Explanation:
Percentage of aggregate = 94%
Specific gravity = 2.65
Specific gravity of asphalt = 1.9
Density of mix = 147pcf = 147lb/ft³
Total weight of mix: (volume = 1ft³)
= (147lb/ft³)(1ft³)
= 147lb
Percentage weight of asphalt in<u> mix:</u>
100% - 94%
= 6%
Weight of asphalt binders
= 6% x 147lb
= 8.82lb
Weight of aggregate in mix:
= 94% x 147
= 138.18lb
Specific weight of asphalt binder:
(Gab)(Yw)
Yw = specific Weight of water
= 62.4lb
Gab = specific gravity of asphalt binder
= 1.0
(62.4lb)(1.0)
= 62.4 lb/ft³
Volume of asphalt in binder:
8.82/62.4
= 0.14ft³
Specific weight of binder in mix:
2.65 x 62.4lb/ft³
= 165.36 lb/ft³
Volume of aggregate:
= 138.18/165.36
= 0.84ft³
Volume of void in the mix:
1ft³ - 0.84ft³ - 0.14ft³
= 0.02ft³
<u>The percentage of void in total mix:</u>
VTM = (0.02ft³/1ft³)100
= 2.0%