The circumference of the circle is 94.25 inches
The area of the circle is 706.86 inches
V^2 = u^2 - 2gh; where v is the final speed, u is the initial speed, g = 9.8 m/s = 0.54 ft/min is the accerelation due to gravity, h = height.
At the maximum height, the final speed is 0.
u^2 = 2gh = 2 x 0.54 x 36 = 38.58
u = sqrt(38.58) = 6.21 ft/min
Therefore, the stne should be thrown with 6.21 ft/min
9514 1404 393
Answer:
$400
Step-by-step explanation:
If the price after taking 25% off is $300, then $300 is 75% of the original price.
$300 = 0.75p
$300/0.75 = p = $400
The original price was $400.
_____
<em>Check</em>
0.25 × $400 = $100
$400 -100 = $300 . . . . the price after taking 25% off
Answer:
Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished