Since the armature is wave wound, the magnetic flux per pole is 0.0274 Weber.
<u>Given the following data:</u>
- Number of armature conductors = 144 slots
- Number of poles = 4 poles
- Number of parallel paths = 2
To find the magnetic flux per pole:
Mathematically, the emf generated by a DC generator is given by the formula;
× 
<u>Where:</u>
- E is the electromotive force in the DC generator.
- Z is the total number of armature conductors.
- N is the speed or armature rotation in r.p.m.
- P is the number of poles.
- A is the number of parallel paths in armature.
First of all, we would determine the total number of armature conductors:
×
× 
Z = 864
Substituting the given parameters into the formula, we have;
× 
× 
<em>Magnetic flux </em><em>=</em><em> 0.0274 Weber.</em>
Therefore, the magnetic flux per pole is 0.0274 Weber.
Read more: brainly.com/question/15449812?referrer=searchResults
Answer: Pi= 4 - 4/3 + 4/5 - 4/7 + 4/9 ...
Explanation:
Is the same as the example,
If Π/4 = 1 - 1/3 + 1/5 - 1/7 + 1/9 ...
Then
(Π/4 )*4= 4*(1 - 1/3 + 1/5 - 1/7 + 1/9 ...)
Π =4 - 4/3 + 4/5 - 4/7 + 4/9 ...
The way to write this is
Sum(from n=0 to n=inf) of (-1)^n 4/(2n+1)
(photo)
Answer:
Explanation:
Given data:
initial construction co = 0.286 wt %
concentration at surface position cs = 0 wt %
carbon concentration cx = 0.215 wt%
time = 7 hr

for 0.225% carbon concentration following formula is used

where, erf stand for error function




from the table erf(Z) value = 0.751 lie between (z) = 0.80 and z = 0.85 so by inteerpolation we have z = 0.815
from given table



x = 0.002395 mm
The answer is choice C
Explanation:
As during construction ,the site is cleared for all debris before laying out the foundation. Even the sewer lines are dug out .
So it will be useful for the construction crews to connect the pipes to the sewer lines before the foundation is poured.
But usually the steps take in construction activity is:- first the site is cleared for the foundation to be poured and once the foundation wall is set , then all utilities , including plumbing and electrical activities are done.,
After this process is over, the city inspector comes to check whether the foundation has been laid down as per the code of construction.
Only after that the rest of the construction activity follows through.