Answer:
cross-weight is used to tighten it up.
Explanation:
and yes this is important because Cross-weight percentage compares the diagonal weight totals to the car's total weight.
hope this help
(mark this answer as an brainliest answer)
The main objective of phasing out an INDUCTION MOTOR is to identify the ends of the stator coils.
<h3>What is an induction motor?</h3>
An induction motor is a device based on alternate electricity (AC) which is composed of three different stator coils.
An induction motor is a device also known as an asynchronous motor due to its irregular velocity.
In conclusion, the objective of phasing out an INDUCTION MOTOR is to identify the ends of the stator coils.
Learn more on induction motors here:
brainly.com/question/15721280
#SPJ1
Answer:
D
Explanation: She hopes to be able to make this, however she hasn't yet...therefore she is thinking of a concept and it's development
Answer:
<em> - 14.943 W/m^2K ( negative sign indicates cooling ) </em>
Explanation:
Given data:
Area of FPC = 4 m^2
temp of water = 60°C
flow rate = 0.06 l/s
ambient temperature = 8°C
exit temperature = 49°C
<u>Calculate the overall heat loss coefficient </u>
Note : heat lost by water = heat loss through convection
m*Cp*dT = h*A * ( T - To )
∴ dT / T - To = h*A / m*Cp ( integrate the relation )
In (
) = h* 4 / ( 0.06 * 10^-3 * 1000 * 4180 )
In ( 41 / 52 ) = 0.0159*h
hence h = - 0.2376 / 0.0159
= - 14.943 W/m^2K ( heat loss coefficient )
The answer is choice C
Explanation:
As during construction ,the site is cleared for all debris before laying out the foundation. Even the sewer lines are dug out .
So it will be useful for the construction crews to connect the pipes to the sewer lines before the foundation is poured.
But usually the steps take in construction activity is:- first the site is cleared for the foundation to be poured and once the foundation wall is set , then all utilities , including plumbing and electrical activities are done.,
After this process is over, the city inspector comes to check whether the foundation has been laid down as per the code of construction.
Only after that the rest of the construction activity follows through.