Sheeeeeesh bro same name ayoooo??
Answer:
Bottom-up Estimation
Explanation:
Bottom-up estimation is a type of project cost estimation that considers the cost of individual project activities and finally sums them up or finds the aggregates. The summation gives an idea of what the entire project will cost.
This is an effective way of estimating the cost of a project as it evaluates the costs on a wholistic basis. It also considers the tiniest details during the estimation process. The process moves from the simpler details to the more complicated details.
Explanation:
i think option 4 is correct answer because itsrelated to animal not plants.
The answer is choice C
Explanation:
As during construction ,the site is cleared for all debris before laying out the foundation. Even the sewer lines are dug out .
So it will be useful for the construction crews to connect the pipes to the sewer lines before the foundation is poured.
But usually the steps take in construction activity is:- first the site is cleared for the foundation to be poured and once the foundation wall is set , then all utilities , including plumbing and electrical activities are done.,
After this process is over, the city inspector comes to check whether the foundation has been laid down as per the code of construction.
Only after that the rest of the construction activity follows through.
Answer:
8*10000+3*1000+1*00+2*10+2
Explanation: