Answer:

Explanation:
From the question we are told that
Pressurized air pressure is 
Atmospheric pressure is 
Initial acceleration of the water rocket is 
Acceleration of the water rocket is 
Mass of water is 
Generally total mass is given mathematically given as

Generally the tension on the rocket is given mathematically given as


T is also

Therefore





therefore diameter of nozzle is mathematically given as

Electricity and magnetism are essentially two aspects of the same thing, because a changing electric field creates a magnetic field, and a changing magnetic field creates an electric field
Explanation:
(Can I please have Brainiest? :)
PART a)
Momentum is defined as product of mass and velocity
so here initial momentum is

given that
m = 0.3 kg
v = 18 m/s

towards East
Part b)
Since puck was initially at rest so here initial momentum must be ZERO
so here to find the force we can use

so here we have
time interval = 0.25 s
now from above equation


Part c)
Due to friction the puck lose its speed by 5 m/s
final speed = 18 - 5 = 13 m/s
mass = 0.3 kg
final momentum = (0.3)(13) = 3.9 kg m/s
now the impulse due to friction force is given as


Part d)
initial momentum of block will be ZERO as it is placed at rest
Initial momentum of the puck is given as

so total momentum before collision is given as

Part e)
since the system is isolated and there is no external force on it
So here momentum will remain conserved
so here we have




so final combined speed will be 2.6 m/s
Answer:
Predictive
Explanation:
There is a wide variety of life cycles applicable to project management. In this regard, we currently have as a reference two somewhat extreme approaches that mark two very different ways of dealing with projects. The predictive approach and the agile approach.
A predictive approach involves a great effort in initial planning and re-planning every time changes are accepted in the project. Therefore, this approach is recommended for changing but not highly changing environments. Although this approach is applicable to any type of project, clear examples of application would be the construction of a subway line, a bridge, the development of critical software. That is, projects where correct and detailed planting is key.