Answer: The overhead percentage is 7.7%.
Explanation:
We call overhead, to all those bytes that are delivered to the physical layer, that don't carry real data.
We are told that we have 700 bytes of application data, so all the other bytes are simply overhead, i.e. , 58 bytes composed by the transport layer header, the network layer header, the 14 byte header at the data link layer and the 4 byte trailer at the data link layer.
So, in order to assess the overhead percentage, we divide the overhead bytes between the total quantity of bytes sent to the physical layer, as follows:
OH % = (58 / 758) * 100 = 7.7 %
Answer:

Explanation:
From the question we are told that:
Initial Pressure 
Initial Temperature 
Final Pressure 
Final Temperature 
Work Output 
Generally Specific Energy from table is
At initial state


With
Specific Volume 
At Final state


Generally the equation for The Process is mathematically given by

Assuming Mass to be Equal

Where



Therefore


The project or the site manager is responsible for monitoring or verifying the aspects of the construction process.
The site or the project manager is the individual that is responsible for the adherence to quality and guidance on the construction site.
The site or project manager has the following tasks
- ensuring safety on the site
- Monitoring the progress or the work that is being done
- Sourcing materials
- Solving problems
In conclusion, the project manager monitors and verifies aspects of the construction process.
Read more on brainly.com/question/24887827?referrer=searchResults