Answer: The energy system related to your question is missing attached below is the energy system.
answer:
a) Work done = Net heat transfer
Q1 - Q2 + Q + W = 0
b) rate of work input ( W ) = 6.88 kW
Explanation:
Assuming CPair = 1.005 KJ/Kg/K
<u>Write the First law balance around the system and rate of work input to the system</u>
First law balance ( thermodynamics ) :
Work done = Net heat transfer
Q1 - Q2 + Q + W = 0 ---- ( 1 )
rate of work input into the system
W = Q2 - Q1 - Q -------- ( 2 )
where : Q2 = mCp T = 1.65 * 1.005 * 293 = 485.86 Kw
Q2 = mCp T = 1.65 * 1.005 * 308 = 510.74 Kw
Q = 18 Kw
Insert values into equation 2 above
W = 6.88 Kw
Answer:
A. Identify the need, recognize limitations of current toothpaste containers, and then brainstorm ideas on how to improve the existing
Explanation:
To design an improved toothpaste container, we must identify the needs of the customer, one of the major need is to make the container attractive to the sight. This is the first thing that will prompt a customer to wanting to buy the product (The reflectance/appearance).
Then recognize the limitation of the current design, what needed change. This will help in determining what is needed to be included and what should be removed based on identified customers need.
The last step is to brainstorm ideas on how to improve the existing designs. Get ideas from other colleagues because there is a saying that two heads are better than one. This will help in coming to a reasonable conclusion on the new design after taking careful consideration of people's opinion.
Moisture content is measured in terms of pounds of water per pound of air (lb water/lb air) or grains of water per pound of air (gr. of water/lb air).
Hope this helps❤
The answer is choice C
Explanation:
As during construction ,the site is cleared for all debris before laying out the foundation. Even the sewer lines are dug out .
So it will be useful for the construction crews to connect the pipes to the sewer lines before the foundation is poured.
But usually the steps take in construction activity is:- first the site is cleared for the foundation to be poured and once the foundation wall is set , then all utilities , including plumbing and electrical activities are done.,
After this process is over, the city inspector comes to check whether the foundation has been laid down as per the code of construction.
Only after that the rest of the construction activity follows through.
Sam, Elijah, Joy Those are 100% correct from my human knowledge