Answer:
why you doin this
Explanation:
is this so we get free points?
The answer is choice C
Explanation:
As during construction ,the site is cleared for all debris before laying out the foundation. Even the sewer lines are dug out .
So it will be useful for the construction crews to connect the pipes to the sewer lines before the foundation is poured.
But usually the steps take in construction activity is:- first the site is cleared for the foundation to be poured and once the foundation wall is set , then all utilities , including plumbing and electrical activities are done.,
After this process is over, the city inspector comes to check whether the foundation has been laid down as per the code of construction.
Only after that the rest of the construction activity follows through.
Answer:

Explanation:
From the question we are told that:
Temperature of silicon 
Electron concentration 
Electron diffusion coefficient is
Electron mobility is 
Electron current density 
Generally the equation for the semiconductor is mathematically given by

Therefore



Answer:
hello your question is incomplete attached below is the complete question
A) overall mean = 5.535, standard deviation ≈ 0.3239
B ) upper limit = 5.85, lower limit = 5.0
C) Not all the samples meet the contract specifications
D) fluctuation ( unstable Asphalt content )
Explanation:
B) The daily average asphalt content has to obtained in order to determine the upper and lower control limits using an average asphalt content of 5.5% +/- 0.5% everyday
The upper limit : 14 may = ( 5.8 + 5.1 ) / 2 = 5.85
The lower limit : 16 may = ( 5.2 + 4.8 ) / 2 = 5.0
attached below is the required plot
C ) Not all the samples meet the contract specifications and the samples that do not meet up are samples from :
15 may and 16 may . this is because their Asphalt contents are 6.2 and 4.8 respectively and sample number 18 and 20
D ) what can be observed is that the ASPHALT content fluctuates between the dates while the contract specification is fixed