Answer:
1) 4.361 x 10 raised to power 8 revolutions
2) 1.744 x 10 raised to power 9 firings
3) 2.18 x 10 raised to power 8 intake strokes
Explanation:
The step by step explanation is as shown in the attachment
Answer: Create lessons learned at the end of the project.
Explanation:
Lessons learned are the experiences that are gotten from a project which should be taken into account for the future projects. Lesson learned are created at the end of the project.
The main objective of the lessons learned is that they show both the positive experience and the negative experience of a project and this will help the future projects that will be undertaken.
Answer:
non-functional requirement,
Yes they can.
The application loading time is determined by testing system under various scenarios
Explanation:
non-functional requirement are requirements needed to justify application behavior.
functional requirements are requirements needed to justify what the application will do.
The loading time can be stated with some accuracy level after testing the system.
The exit temperature is 586.18K and compressor input power is 14973.53kW
Data;
- Mass = 50kg/s
- T = 288.2K
- P1 = 1atm
- P2 = 12 atm
<h3>Exit Temperature </h3>
The exit temperature of the gas can be calculated isentropically as

Let's substitute the values into the formula

The exit temperature is 586.18K
<h3>The Compressor input power</h3>
The compressor input power is calculated as

The compressor input power is 14973.53kW
Learn more on exit temperature and compressor input power here;
brainly.com/question/16699941
brainly.com/question/10121263
Answer:
C = 0.22857 ng / m³
Explanation:
Let's solve this problem for part the total time in the kitchen is
t = 2h (60 min / 1h) = 120 min
The concentration (C) quantity of benzol pyrene is the initial quantity plus the quantity generated per area minus the quantity eliminated by the air flow. The amount removed can be calculated assuming that an amount of extra air that must be filled with the pollutant
amount generated
C = co + time_generation rate / (area_house + area_flow)
C = 0.2 + 0.01 120 / (40+ 2)
C = 0.22857 ng / m³