CORRECTLY PLACED:
Large-lite glazing requires consideration of the following (select all that apply)
a. glazing must be supported without imparting stresses.
b. glazing must be supported against wind loads.
c. gaskets must separate glazing and frame.
d. glazing must be vacuum-insulated e. weep holes must be provided in the horizontal mullions.
Answer: a, b, c and e.
Explanation:
When large-lite glazing is done, options a, b, c and e must be considered. But vacuum-insulation isn't necessary, so option d. isn't part of the considerations.
Answer:
Explanation:
from figure
taking summation of force in x direction be zero
.....1
taking summation of force in Y direction be zero
.........2
putting T value in equation 1
.........3
Water at 10 degree C has kinetic viscosity v = 1.3 \times 10^{-6} m^2/s
Reynold number
so for Re = cd is 0.072
degree
Answer:
for...?
thenks for the points :))
Answer:
C. The intensity of 20F signal would be higher, but the lifetime would be unchanged
Explanation:
The half live value is constant, life term of an exponentially decaying quantity, and it a property of the exponential decay equation. Half life does not decay on the initial concentration. Hence, there won't be any change in observation.
C. The intensity of 20F signal would be higher, but the lifetime would be unchanged
Answer:
c) site preparation
Explanation:
A construction process can be defined as a series of important physical events (processes) that must be accomplished during the execution of a construction project.
Generally, in the construction of any physical asset such as offices, hospitals, schools, stadiums etc, the first step of the construction process is site preparation. Site preparation refers to processes such as clearing, blasting, levelling, landfilling, surveying, cutting, excavating and demolition of all unwanted objects on a piece of land, so as to make it ready for use.
This ultimately implies that, site preparation should be the first task to be accomplished in the construction process.
Hence, the construction process typically begins with site preparation before other activities such as the laying of foundation can be done.
Additionally, construction costs can be defined as the overall costs associated with the development of a built asset, project or property. The construction costs is classified into two (2) main categories and these are; capital and operational costs.