Answer:
final volume V2 = 0.71136 m³
work done in process W = -291.24 kJ
heat transfer Q = 164 kJ
Explanation:
given data
mass = 1.5 kg
pressure p1 = 200 kPa
temperature t1 = 150°C
final pressure p2 = 600 kPa
final temperature t2 = 350°C
solution
we will use here superheated water table that is
for pressure 200 kPa and 150°C temperature
v1 = 0.95964 m³/kg
u1 = 2576.87 kJ/kg
and
for pressure 600 kPa and 350°C temperature
v2 = 0.47424 m³/kg
u2 = 2881.12 kJ/kg
so v1 is express as
V1 = v1 × m ............................1
V1 = 0.95964 × 1.5
V1 = 1.43946 m³
and
V2 = v2 × m ............................2
V2 = 0.47424 × 1.5
final volume V2 = 0.71136 m³
and
W = P(avg) × dV .............................3
P(avg) =
=
= 400 × 10³
put here value
W = 400 × 10³ × (0.71136 - 1.43946 )
work done in process W = -291.24 kJ
and
heat transfer is
Q = m × (u2 - u1) + W .............................4
Q = 1.5 × (2881.12 - 2576.87) + 292.24
heat transfer Q = 164 kJ
Answer:
LAOD = 6669.86 N
Explanation:
Given data:
width
thickness 
crack length 2c = 0.5 mm at centre of specimen

stress intensity factor = k will be


we know that

[c =0.5/2 = 2.5*10^{-4}]
K = 0.1724 Mpa m^{1/2} for 1000 load
if
then load will be




LAOD = 6669.86 N
Answer:3.47 m
Explanation:
Given
Temperature(T)=300 K
velocity(v)=1.5 m/s
At 300 K


And reynold's number is given by



x=3.47 m
Measure the longest circuit and add 50% for fittings and terminal units.
The answer is choice C
Explanation:
As during construction ,the site is cleared for all debris before laying out the foundation. Even the sewer lines are dug out .
So it will be useful for the construction crews to connect the pipes to the sewer lines before the foundation is poured.
But usually the steps take in construction activity is:- first the site is cleared for the foundation to be poured and once the foundation wall is set , then all utilities , including plumbing and electrical activities are done.,
After this process is over, the city inspector comes to check whether the foundation has been laid down as per the code of construction.
Only after that the rest of the construction activity follows through.