Answer:
a. 9947 m
b. 99476 times
c. 2*10^11 molecules
Explanation:
a) To find the mean free path of the air molecules you use the following formula:
R: ideal gas constant = 8.3144 Pam^3/mol K
P: pressure = 1.5*10^{-6} Pa
T: temperature = 300K
N_A: Avogadros' constant = 2.022*10^{23}molecules/mol
d: diameter of the particle = 0.25nm=0.25*10^-9m
By replacing all these values you obtain:
b) If we assume that the molecule, at the average, is at the center of the chamber, the times the molecule will collide is:
c) By using the equation of the ideal gases you obtain:
Answer:
It studies the process of technological change. Under the field of Technology Dynamics the process of technological change is explained by taking into account influences from "internal factors" as well as from "external factors
Explanation:
The total present worth is $19,783.01
The present worth of a series of cash flow is the value of the cash flows in year 0 (today)
Cash flow in year 0 = 5330
Cash flow in year 1 = 0
Cash flow in year 2 = 0
Cash flow in year 3 = 13075 / (1.02)^3 = 12,320.86
Cash flow in year 4 = 2308 / (1.02)^4 = 2,132.24
Present worth = $19,783.01
A similar question was solved here: brainly.com/question/9641711?referrer=searchResults
Answer:
A
Explanation:
Due to ethanol's lower energy content, FFVs operating on E85 get roughly 15% to 27% fewer miles per gallon than when operating on regular gasoline, depending on the ethanol content.
The answer is choice C
Explanation:
As during construction ,the site is cleared for all debris before laying out the foundation. Even the sewer lines are dug out .
So it will be useful for the construction crews to connect the pipes to the sewer lines before the foundation is poured.
But usually the steps take in construction activity is:- first the site is cleared for the foundation to be poured and once the foundation wall is set , then all utilities , including plumbing and electrical activities are done.,
After this process is over, the city inspector comes to check whether the foundation has been laid down as per the code of construction.
Only after that the rest of the construction activity follows through.