Answer:
trick question - they are both right.
Explanation:
Both valves are closed during compression and power stroke or both strokes would be useless.
The difference between the baseband and the broadband connection is made with the transmission of signal over the frequency.
<h3 /><h3>What is data transmission?</h3>
The data transmission is given as the transfer of the data from one digital device to another. The transmission can take place with the baseband transmission and the broadband transmission.
The major difference between the two transmissions is that the baseband utilizes a complete frequency for transmission of signal, while the transmission with the broadband is made with multiple signals over multiple frequencies.
Learn more about broadband signals, here:
brainly.com/question/19204110
#SPJ1
Answer:
A) m' = 351.49 kg/s
B) m'= 1036.91 kg/s
Explanation:
We are given;
Pressure Ratio;r_p = 12
Inlet temperature of compressor;T1 = 300 K
Inlet temperature of turbine;T3 = 1000 K
cp = 1.005 kJ/kg·K
k = 1.4
Net power output; W' = 70 MW = 70000 KW
A) Now, the formula for the mass flow rate using the total power output of the compressor and turbine is given as;
m' = W'/[cp(T3(1 - r_p^(-(k - 1)/k)) - T1(r_p^((k - 1)/k))
At, 100% efficiency, plugging in the relevant values, we have;
m' = 70000/(1.005(1000(1 - 12^(-(1.4 - 1)/1.4)) - 300(12^((1.4 - 1)/1.4)))
m' = 70000/199.1508
m' = 351.49 kg/s
B) At 85% efficiency, the formula will now be;
m' = W'/[cp(ηT3(1 - r_p^(-(k - 1)/k)) - (T1/η) (r_p^((k - 1)/k))
Where η is efficiency = 0.85
Thus;
m' = 70000/(1.005(0.85*1000(1 - 12^(-(1.4 - 1)/1.4)) - (300/0.85)(12^((1.4 - 1)/1.4)))
m' = 70000/(1.005*(432.09129 - 364.9189)
m'= 1036.91 kg/s
Answer:
c) site preparation
Explanation:
A construction process can be defined as a series of important physical events (processes) that must be accomplished during the execution of a construction project.
Generally, in the construction of any physical asset such as offices, hospitals, schools, stadiums etc, the first step of the construction process is site preparation. Site preparation refers to processes such as clearing, blasting, levelling, landfilling, surveying, cutting, excavating and demolition of all unwanted objects on a piece of land, so as to make it ready for use.
This ultimately implies that, site preparation should be the first task to be accomplished in the construction process.
Hence, the construction process typically begins with site preparation before other activities such as the laying of foundation can be done.
Additionally, construction costs can be defined as the overall costs associated with the development of a built asset, project or property. The construction costs is classified into two (2) main categories and these are; capital and operational costs.