Answer:I have no clue if you find out let me know
Explanation:
Answer:
The head loss in Psi is 0.390625 psi.
Explanation:
Fluid looses energy in the form of head loss. Fluid looses energy in the form of head loss when passes through the valve as well.
Given:
Factor cv is 48.
Flow rate of water is 30 GPM.
GPM means gallon per minute.
Calculation:
Step1
Expression for head loss for the water is given as follows:

Here, cv is valve coefficient, Q is flow rate in GPM and h is head loss is psi.
Step2
Substitute 48 for cv and 30 for Q in above equation as follows:


h = 0.390625 psi.
Thus, the head loss in Psi is 0.390625 psi.
Answer:
Atlantis benefited from lessons learned in the construction and testing of Enterprise, Columbia and Challenger. ... The Experience gained during the Orbiter assembly process also enabled Atlantis to be completed with a 49.5 percent reduction in man hours (compared to Columbia).
Explanation:
Where are the statements then bbs lol
The answer is choice C
Explanation:
As during construction ,the site is cleared for all debris before laying out the foundation. Even the sewer lines are dug out .
So it will be useful for the construction crews to connect the pipes to the sewer lines before the foundation is poured.
But usually the steps take in construction activity is:- first the site is cleared for the foundation to be poured and once the foundation wall is set , then all utilities , including plumbing and electrical activities are done.,
After this process is over, the city inspector comes to check whether the foundation has been laid down as per the code of construction.
Only after that the rest of the construction activity follows through.