Answer:

Explanation:
Lets take the numerator of the fraction to be = x
So the denominator of the fraction is 4 more than the numerator = x+4
The fraction is ;
Now add 4 to the numerator and add 7 to the denominator as;

This new fraction is equal to 1 half =1/2
write the equation as;

perform cross-product
2(x+4 )=1( x+11 )
2x+8 = x + 11
2x-x = 11-8
x=3
The original fraction is;

The pressure difference across the sensor housing will be "95 kPa".
According to the question, the values are:
Altitude,
Speed,
Pressure,
The temperature will be:
→ ![T = 15.04-[0.00649(9874)]](https://tex.z-dn.net/?f=T%20%3D%2015.04-%5B0.00649%289874%29%5D)
→ 
→ 
now,
→ ![P_o = 101.29[\frac{(-49.042+273.1)}{288.08} ]^{(5.256)}](https://tex.z-dn.net/?f=P_o%20%3D%20101.29%5B%5Cfrac%7B%28-49.042%2B273.1%29%7D%7B288.08%7D%20%5D%5E%7B%285.256%29%7D)
→
hence,
→ The pressure differential will be:
= 
= 
Thus the above solution is correct.
Learn more about pressure difference here:
brainly.com/question/15732832
Answer:
1. You have the courage to help without expecting a reward.
2. Because actions are more eloquent than words. Actions are far more valuable and counted than words, and that's how she inspired me.
3. Doing simple things that can make someone grateful and happy without knowing that someone is inspired and motivated by your good deeds, and also doing some interesting things By.
Explanation:
The answer is choice C
Explanation:
As during construction ,the site is cleared for all debris before laying out the foundation. Even the sewer lines are dug out .
So it will be useful for the construction crews to connect the pipes to the sewer lines before the foundation is poured.
But usually the steps take in construction activity is:- first the site is cleared for the foundation to be poured and once the foundation wall is set , then all utilities , including plumbing and electrical activities are done.,
After this process is over, the city inspector comes to check whether the foundation has been laid down as per the code of construction.
Only after that the rest of the construction activity follows through.