Answer:
c) site preparation
Explanation:
A construction process can be defined as a series of important physical events (processes) that must be accomplished during the execution of a construction project.
Generally, in the construction of any physical asset such as offices, hospitals, schools, stadiums etc, the first step of the construction process is site preparation. Site preparation refers to processes such as clearing, blasting, levelling, landfilling, surveying, cutting, excavating and demolition of all unwanted objects on a piece of land, so as to make it ready for use.
This ultimately implies that, site preparation should be the first task to be accomplished in the construction process.
Hence, the construction process typically begins with site preparation before other activities such as the laying of foundation can be done.
Additionally, construction costs can be defined as the overall costs associated with the development of a built asset, project or property. The construction costs is classified into two (2) main categories and these are; capital and operational costs.
Answer:
a) V = 0.354
b) G = 25.34 GPA
Explanation:
Solution:
We first determine Modulus of Elasticity and Modulus of rigidity
Elongation of rod ΔL = 1.4 mm
Normal stress, δ = P/A
Where P = Force acting on the cross-section
A = Area of the cross-section
Using Area, A = π/4 · d²
= π/4 · (0.0020)² = 3.14 × 10⁻⁴m²
δ = 50/3.14 × 10⁻⁴ = 159.155 MPA
E(long) = Δl/l = 1.4/600 = 2.33 × 10⁻³mm/mm
Modulus of Elasticity Е = δ/ε
= 159.155 × 10⁶/2.33 × 10⁻³ = 68.306 GPA
Also final diameter d(f) = 19.9837 mm
Initial diameter d(i) = 20 mm
Poisson said that V = Е(elasticity)/Е(long)
= - <u>( 19.9837 - 20 /20)</u>
2.33 × 10⁻³
= 0.354,
∴ v = 0.354
Also G = Е/2. (1+V)
= 68.306 × 10⁹/ 2.(1+ 0.354)
= 25.34 GPA
⇒ G = 25.34 GPA
All of the dimensions on an aircraft drawing are _________ to the bottom of the drawing
Answer: parallel
Answer:
the answer how you analyzs the problwm